Valorization clauses must not be illusory. Planned debates with the Public Procurement Office.

👷‍♂️Price changes in the market disadvantage construction contract contractors, who point to improper practices in road construction proceedings.The President of the Public Procurement Office is open to talks, which are scheduled for the fall.

👷‍♂️ “The Public Procurement Law requires that in contracts for construction works concluded for a period longer than 12 months, the contracting authority should provide rules for introducing changes in the amount of the contractor’s remuneration in case of changes in the price of materials or costs related to the execution of the contract (…),” comments attorney Jacek Liput.

https://www.prawo.pl/biznes/waloryzacja-wynagrodzenia-nie-moze-byc-pozorna-potrzebne-sa,510180.html?fbclid=IwAR0f9r0ZlH7p9SnBFoHSZXVk62wNXdZztQRtLlb_Re-XWnt9UnvksbYEPto

—kontakt

GP Partners
Gawroński, Biernatowski Sp.K.

T: +48 22 243 49 53

E: info@gppartners.pl

Al. Jana Pawła II 12

00-124 Warszawa

Newsletter

Nasz newsletter to stałe źródło bieżących informacji z zakresu technologii, regulacji, sporów i prawa. 

Ilustracja do „Cyberiady” Stanisława Lema, Daniel Mróz ©za zgodą Łucji Mróz-Raynoch
Ilustracja do „Cyberiady” Stanisława Lema, Daniel Mróz ©za zgodą Łucji Mróz-Raynoch